Cart Road 52 Bridge Project – Update

Want create site? Find Free WordPress Themes and plugins.

Cart Road 52 Bridge Project

This scheme will link the footways in Hailey Park and those running west of the river to link with the Taff Trail. The contract has now been awarded and the works are planned to start week commencing 15 October 2012.

The works is scheduled for 16 weeks depending on the weather condition. It consists of the refurbishment of the bridge deck; removing the existing cantilevered walkways, parapets and stone ballast; steelwork repair; surface preparation; repainting and a new bridge deck surface and drainage system The scheme has been predominately funded by S.106 monies received from the development at Radyr sidings.